Question: Consider this process: Operation 1- 2 workers (12 minutes), Operation 2- 1 worker (6 minutes) Operation 3- 2 workers (6 minutes). If the process is

Consider this process: 

Operation 1- 2 workers (12 minutes), 

Operation 2- 1 worker (6 minutes)

 Operation 3- 2 workers (6 minutes).

If the process is operating at capacity, what is the utilization of the workers in operation 3?