Question: - Consider this system: - Aisle is 400ft long and 100ft high -1/O point is in the lower left position - S/R machine travels at
- Consider this system: - Aisle is 400ft long and 100ft high -1/O point is in the lower left position - S/R machine travels at 40fpm horizontally and 15fpm vertically - Time required to pickup or deposit a load is 0.8 minutes - Assume single command operation - Find T[SC]. How many operations per hour