Question: Consider two mutually exclusive projects, find the crossover rate and choose the right answer: Project A Project B 1000 -300 -500 -300 Year 0
Consider two mutually exclusive projects, find the crossover rate and choose the right answer: Project A Project B 1000 -300 -500 -300 Year 0 1 2 3 900 -650 -200 -100 a. The crossover rate is 4.91% and for a discount rate greater than the crossover rate I select project A b. The crossover rate is 4.91% and for a discount rate greater than the crossover rate I select project B c. The crossover rate is 6.72% and for a discount rate greater than the crossover rate I select project A d. The crossover rate is 6.72% and for a discount rate greater than the crossover rate I select project B
Step by Step Solution
3.40 Rating (156 Votes )
There are 3 Steps involved in it
To find the crossover rate we need to determine the disc... View full answer