Question: Consider two mutually exclusive R&D projects that ADM is considering. Assume the discount rate for ADM is 12 percent. Project A: Server CPU .13 micron
| Consider two mutually exclusive R&D projects that ADM is considering. Assume the discount rate for ADM is 12 percent. |
| Project A: | Server CPU .13 micron processing project |
| By shrinking the die size to .13 micron, ADM will be able to offer server CPU chips with lower power consumption and heat generation, meaning faster CPUs. |
| Project B: | New telecom chip project |
| Entry into this industry will require introduction of a new chip for cell phones. The know-how will require a large amount of up-front capital, but success of the project will lead to large cash flows later on. |
| Year | Project A | Project B | ||||||||||||||||||||||||||||||||||||||||
| 0 | $ | 735,000 | $ | 943,000 | ||||||||||||||||||||||||||||||||||||||
| 1 | 346,000 | 261,000 | ||||||||||||||||||||||||||||||||||||||||
| 2 | 364,000 | 369,000 | ||||||||||||||||||||||||||||||||||||||||
| 3 | 258,000 | 366,000 | ||||||||||||||||||||||||||||||||||||||||
| 4 | 183,000 | 419,000 | ||||||||||||||||||||||||||||||||||||||||
| 5 | 126,000 | 504,000 | ||||||||||||||||||||||||||||||||||||||||
|
| ||||||||||||||||||||||||||||||||||||||||||