Question: Consider two projects, 1 and 2 , to be completed by a team of experts, and they can do only one project at a time.
Consider two projects, and to be completed by a team of experts, and they can do only one project
at a time. It takes days to complete project whereas the time of project is days. If the project
is switched from to then the setup takes days. On the other hand, if the project is switched
from to then the setup reduces to day. The projects cannot start before Day and both projects
must be completed on or before Day Let x and x be the start date in days for projects and
Two projects will not be processed concurrently:
If precedes then the start date of must be greater than or equal to start date of plus the
working time of and the setup time.
If precedes then the start date of must be greater than or equal to start date of plus the
working time of and the setup time.
Use indicator variables representing the order of working of projects and mathematically formulate
the constraints that are verbally written above using indicator variables and big Ms Calculate the
minimum value of M that would work.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock