Question: Consider two projects that have the same activities and the same dependencies. In the first project, the activity times are expected outcomes. The actual times

Consider two projects that have the same activities and the same dependencies. In the first project, the activity times are expected outcomes. The actual times will vary. In the second project, the activity times are always as expected. Assuming the expected activity times are identical across the two projects, which project will be completed first? a. The first b. The second c. Cannot be determined