Question: Consider two real-time tasks T1 and T2, with their processing time t, deadline d, and period p(t,d,p) given as (20,40,40) and (25,65,65), respectively. Which of
Consider two real-time tasks T1 and T2, with their processing time t, deadline d, and period p(t,d,p) given as (20,40,40) and (25,65,65), respectively. Which of the following scheduling algorithms can be used to schedule the tasks without missing their deadlines? Round Robin (RR) Rate monotonic (RM) Alfinity Earliest deadiline-first (EDF)