Question: Consider We Build Construction's latest project: We Build is developing a 1-story medical office building on available land near a hospital. The following table details

Consider We Build Construction's latest project: We Build is developing a 1-story medical office building on available land near a hospital. The following table details the project's 8 work activities.

K

Activity

Duration (days)

Predecessor Activities

1

Foundation

15

2

Concrete slab

3

1

3

Structural members

3

2

4

Roof

7

3

5

Rough electrical

10

3

6

Heating and air conditioning

13

1, 3

7

Walls

18

3, 5, 6

8

Interior finish

20

4, 7

a) After drawing the network based on the provided information (you do not need show the network), compute the early and late activity times, the total slack, and identify the critical path. Please provide me with the following information in order as your answer

The critical path (e.g., 1-2-3-4)

EF for activities 4, 5, 6 and the equation you use

LF for activity 8 and the equation you use

LS for activities 4, 5, 6 and the equation you use

Total slack for activities 2, 3, 8 and the equation you use

b) How will you draw the network if there are multiple starts? Please provide a brief description.

Step by Step Solution

3.41 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

b Critical Path 123678 72 days Slack is not applicable ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Chemical Engineering Questions!