Question: consider whether one process would result in more accuracy than another and discuss why.in the example below. In order to have accurate top-down estimation, historical

consider whether one process would result in more accuracy than another and discuss why.in the example below.

In order to have accurate top-down estimation, historical information must be used, which points to analogous estimating. Using a previous projects actual costs, an estimation using top-down may be done quickly and accurately if the projects are similar. However, estimates will not be accurate if two projects are not similar or only appeared to be similar, but this is an easy way to estimate if there is not much known about the project but has same same attributes as another (MindEdge, 2014).

Contrary to top-down, is the bottom-up estimation. Like the name suggests, the estimation starts from the bottom where those closest to the work are doing the estimation which would make this technique more accurate and higher quality than top-down. Even though this estimation may be more accurate, it also can be more time consuming as it may take longer for those close to the work to complete an estimation in addition to daily responsibilities (MindEdge, 2014).

It is imperative to have an accurate estimation of costs as this can effect resources, timeline of completion and profitability.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!