Question: Considering Net Present Value , IRR & PI , out of the following 6 projects , which are the 3 projects that must be chosen

Considering Net Present Value , IRR & PI , out of the following 6 projects , which are the 3 projects that must be chosen for better financial results

PROJECTS

A convention center

COST

2,500,000

NPV

300,000

IRR

14%

PI

1.12

B Sales & MarketingTie-up

500,000

150,000

20%

1.30

C Suites Addition

4,000,000

500,000

13%

1.13

D - Suites Refurbishment

3,400,000

450,000

15%

1.13

E - GYM Facility

3,000,000

400,000

14%

1.13

F Bar &Restaurant Redesign

3,500,000

300,000

13%

1.09