Question: Considering the project information below, what is the probability that the project will take longer than 12 days? Present all your steps. In your calculations,
Considering the project information below, what is the probability that the project will take longer than 12 days? Present all your steps. In your calculations, round your value of z to 2 decimal places.
| Activity | Immediate predecessors | Time (days) | ||||
| Optimiste | The most probable | Pessimist | ||||
| J | - | 1 | 3 | 5 | ||
| K | J | 1 | 2 | 3 | ||
| L | J | 2 | 3 | 4 | ||
| M | K, L | 3 | 4 | 5 | ||
| N | L | 3 | 4 | 11 |
Step by Step Solution
There are 3 Steps involved in it
Steps 1 Calculate Expected Time and Standard Deviation for Each Activity Expected Time t Optimistic ... View full answer