Considering the project network from the previous question (included below for reference), what is the critical path?
Question 11 5 pts Considering the project network from the previous question (included below for reference), what is the critical path? TaskB 2 weeks Task 8 weeks Task A 3 weeks Task F 7 weeks Task 4 weeks Task E 1 week O A, B, C, D, E, F O A, B, D, F O A, C, D, F O A, C, E, F O A, B, D, F, C, E