Question: construct a net material requirements plan using on hand inventory The demand for subassembly S is 130 units in week 7. Each unit of S
The demand for subassembly S is 130 units in week 7. Each unit of S requires 2 units of T and 1 unil of U. Each unt of T requires 1 unit of V,2 unts of W, and 1 unit of x. Finely, each unil of U 2 weeks to make Y, and 1 week to make Z. Cilck the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory Conatruci a net material requirements plan unng on-hand inventory fontor your responses as whole numbers)