Question: Construct a network activity diagram based on the following information: Activity Duration (DAYS) Predecessors None 4 B D E None 3 5 7 5 F

Construct a network activity diagram based on the
Construct a network activity diagram based on the following information: Activity Duration (DAYS) Predecessors None 4 B D E None 3 5 7 5 F G H B DRE F,G H H 5 10 5 ! 5 10 5 10 L JK M N o L L 5 10 15 20 L P MNO 1. Conduct a forward and backward pass using Activity on the Node (AON) 2. Identify the total duration for the project. 3. Identify the Critical Path 4. Show the Float Calculation which is Late Start minus Early Start

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!