Question: Construct a network for a project having the following activities and activity time: ACTIVITY A B C D E F G PREDECESSOR - - A
Construct a network for a project having the following activities and activity time:
| ACTIVITY | A | B | C | D | E | F | G |
| PREDECESSOR | - | - | A | A | C , B | C , B | D , E |
| TIME ( MONTH ) | 4 | 6 | 2 | 6 | 3 | 3 | 5 |
Find the critical path.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts