Question: Construct a network for the project below and find its expected completion time. table [ [ Activity , t o ( Weeks ) ,

Construct a network for the project below and find its expected completion time.
\table[[Activity,to(Weeks),\table[[Preceding],[activities]]],[a,3,None],[b,5,a],[c,3,a],[d,1,c],[e,3,b],[f,4,b, d],[g,2,c],[h,3,g, f],[i,1,e, h]]
Estimated activity times and precedences are given below:
 Construct a network for the project below and find its expected