Question: Construct a network using the information in the table and identify the critical path. Activity Time Predecessor A 14 B 6 C 19 D

Construct a network using the information in the table and identify the critical path. Activity Time Predecessor A 14 B 6 C 19 D 11 AAB IE 16 B, C IF G H 487 14 ID 18 E, F 7 G Complete the table below: Task Early Early Late Late start finish start finish ABCDEFGH
Step by Step Solution
There are 3 Steps involved in it
Step 1 List of Activities and Dependencies Activity Time Predecessor A 4 B 6 A C 9 A D 11 B E 16 BC ... View full answer