Question: Construct a PERT/CPM chart based on the table below. Determine the critical path. Use the Most Likely Time as the duration for each activity. Ignore

Construct a PERT/CPM chart based on the table below. Determine the critical path.

Use the "Most Likely Time" as the duration for each activity. Ignore the "Most Optimistic Time" and the "Most Pessimistic Time".Construct a PERT/CPM chart based on the table

Activity Most Pessimestic time (b) B D Time-Estimates (in weeks) Preceding Most optimistic Most likely activity time (a) time (m) None 2 4 None 10 12 A 8 9 A 10 15 A 7 7.5 B.C 9 9 D 3 3.5 E,F,G S 5 12 26 10 20 11 9 7 5 E F G H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!