Question: Construct a product structure. Identify all levels, parents, and components (5 marks) Prepare a time-phased product structure (5 marks) Construct a gross material requirements plan

  1. Construct a product structure. Identify all levels, parents, and components (5 marks)
  2. Prepare a time-phased product structure (5 marks)
  3. Construct a gross material requirements plan (10 marks)

Construct a product structure. Identify all

The demand for subassembly R is 200 units in week 8. Each unit of R requires 1 unit of S and 2 units of T. Each unit of S requires 1 unit of U, 2 units of V, and 1 unit of W. Finally, each unit of T requires 2 units of X and 3 units of Y. One firm manufactures all items. It takes 3 weeks to make R, 1 week to make S, 2 weeks to make T, 2 weeks to make U, 3 weeks to make V, 1 week to make W, 2 weeks to make X, and 1 week to make Y. a) Construct a product structure. Identify all levels, parents, and components. (5 marks) b) Prepare a time-phased product structure. (5 marks) c) Construct a gross material requirements plan (10 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!