Question: Construct an AON nefwork according to the activity description below. Libel ac tivities by their letters and node numbers. Remove redundant relationships and arrange activities

Construct an AON nefwork according to the activity description below. Libel ac tivities by their letters and node numbers. Remove redundant relationships and arrange activities in proper sequence steps. Show all calculations.
Activity H is followed by activities V, X, L and Z.
Activity C precedes activity Pand follows the completion of activities Q. I, and I.
The predecessors to activity N are activities 1,K and A.
Activity O follows activities D and x, and preoedes activaty P
Activity I is preceded by activities I, D, and I.
Activity I follows activity If and precedes activity Q
Activity U can start when activities V and x are completed
Activity D follows actrity U
Activity E depends on actwity L. and H Hand precedes Aftavities T. N, and I
Activity M is preceded by activitas x,L, and ??? and is followed by activities A
 Construct an AON nefwork according to the activity description below. Libel

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!