Question: Construct the project network for a project with the following activity list. Determine the earliest and latest activity times and the activity slack for the
Construct the project network for a project with the following activity list. Determine the earliest and latest activity times and the activity slack for the network. Indicate the critical path and the time.

Immediate Estimated Activity Predecessors Duration 1 month 2 months 4 months 3 months 2 months 3 months D. E 5 months 1 month G, H 4 months 2 months 3 months 3 months 5 months 4 months