Question: Construct the project network using the information i n the below table, then find the critical path. [ 2 5 marks ] ? A c

Construct the project network using the information in the below table, then find the critical path.
[25 marks]
?ActivityPredecessor(s)Duration(days)???A:Jobreview-1???B:AdvisecustomersoftemporaryoutageA12???C:RequisitionstoresA1???D:ScoutjobA12???E:SecurepolesandmaterialCD3??F:DistributepolesE312???G:PolelocationcoordinationD12???H:Re-stakeG12???I:DigholesH3???J:FrameandsetpolesFI4??K:CoveroldconductorsJK1??L:PullnewconductorsL2???M:InstallremainingmaterialL2???N:SagconductorD2???O:TrimtreesBMNO2P:De-energizeandswitchlinesP110???Q:EnergizeandswitchnewlineQ12???R:CleanupQ1???S:RemoveoldconductorR1???T:RemoveoldpolesR2???U:Returnmaterialtostores?2???
Construct the project network using the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!