Question: Construction ( or Project ) planning involves which of the following? a . Recognizing project scope b . Work sequencing ( logical order of doing
Construction or Project planning involves which of the following?
a Recognizing project scope
b Work sequencing logical order of doing the work
c Work Breakdown breaking into smaller work packages
d All of the above
Which of the following examples relate to hard logic in activity sequencing?
a cannot place concrete before formwork is completed
b cannot complete electrical conduit work before drain pipe is laid
c can build nd floor before building rd floor
d can complete cladding ie facade or outer covering works before finishing duct work
Changes eg modifications in plans etc. that arise after bid is advertised and before the bid is opened or evaluated can be made through
a Modifications
b Addenda
c Supplementary Conditions
d General Conditions
Which of the following examples relate to soft logic in activity sequencing?
a cannot build floor before building floor
b cannot place concrete before formwork is completed
c cannot complete electrical conduit work before drain pipe is laid
d cannot complete cladding ie facade or outer covering works before finishing duct work
In a competitive bidding process, the award is generally made to the
a lowest bidder
b highest bidder
c lowest responsive bidder
d any random bidder
Which of the following statements is FALSE?
a Invitation to bid or Notice to Bidders is sent out by owners designers.
b Sometimes, only prequalified contractors are allowed to submit bids.
c Bid package doesn't include special conditions
d Construction bonds protect the owner when the contractor defaults.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock