Question: Construction Project Activity Activity Description Immediate Predecessors Estimated Duration A Excavate 2 weeks B Lay the foundation A 4 weeks C Put up the rough
Construction Project
| Activity | Activity Description | Immediate Predecessors | Estimated Duration |
| A | Excavate | 2 weeks | |
| B | Lay the foundation | A | 4 weeks |
| C | Put up the rough wall | B | 10 weeks |
| D | Put up the roof | C | 6 weeks |
| E | Install the exterior plumbing | C | 4 weeks |
| F | Install the interior plumbing | E | 5 weeks |
| G | Put up the exterior siding | D | 7 weeks |
| H | Do the exterior painting | E, G | 9 weeks |
| I | Do the electrical work | C | 7 weeks |
| J | Put up the wallboard | F, I | 8 weeks |
| K | Install the flooring | J | 4 weeks |
| L | Do the interior painting | J | 5 weeks |
| M | Install the exterior fixtures | H | 2 weeks |
| N | Install the interior fixtures | K, L | 6 weeks |
- Draw the project network
- Under normal circumstances, can the project be completed within 40 weeks? Why
- What are the critical activities?
- What is the critical path of the project?
Consider additional information below:
| Activity | Time | Cost | ||
| Normal | Crash | Normal | Crash | |
| A | 2 weeks | 1 week | $180,000 | $280,000 |
| B | 4 weeks | 2 weeks | 320,000 | 420,000 |
| C | 10 weeks | 7 weeks | 620,000 | 860,000 |
| D | 6 weeks | 4 weeks | 260,000 | 340,000 |
| E | 4 weeks | 3 weeks | 410,000 | 570,000 |
| F | 5 weeks | 3 weeks | 180,000 | 260,000 |
| G | 7 weeks | 4 weeks | 900,000 | 1,020,000 |
| H | 9 weeks | 6 weeks | 200,000 | 380,000 |
| I | 7 weeks | 5 weeks | 210,000 | 270,000 |
| J | 8 weeks | 6 weeks | 430,000 | 490,000 |
| K | 4 weeks | 3 weeks | 160,000 | 200,000 |
| L | 5 weeks | 3 weeks | 250,000 | 350,000 |
| M | 2 weeks | 1 week | 100,000 | 200,000 |
| N | 6 weeks | 3 weeks | 330,000 | 510,000 |
e) Formulate an LP Model to determine an optimal crashing for each of the activities in order to complete the project within 40 weeks