Question: Construction project management , please solve this issue as soon as possible and give me the solution Ql. Based on the table below, solve the
Ql. Based on the table below, solve the questions (1-4), (12 Marks) Activity Predecessor Optimistic Most Likely Duration Duration 2 4 B 5 8 H B 1 2 H 4 10 D B 4 7 E 11 14 F DE 9 13 G EE 2 5 Pessimistic Duration 10 15 3 12 9 21 7 1. What is the probability that the project finishes in less than 10 days 2. What is the probability that the Activity "G" finishes between 3 and 5 days 3. Estimate project completion date with at least a 96% confidence level 4 What is the probability that node "D" has a float more than Zero
Step by Step Solution
There are 3 Steps involved in it