Question: Continuing on from the previous question (table below is identical to the one in the previous question - duration in weeks), suppose you are the

Continuing on from the previous question (table below is identical to the one in the previous question - duration in weeks), suppose you are the project manager of the project whose activities are depicted in the table. Today is the end of Week 7, and your team lead tells you that Activity D needs four more full weeks to complete. The next day you receive an email from your project sponsor inquiring whether you expect the project to complete on schedule (within the time you determined in the previous question). What would your email reply to your sponsor be? Question 32 options: "Yes, we will nish on or ahead of schedule" "There's an 80% chance we will finish on schedule" "Unfortunately, we will slip the schedule slightly" "Frankly, it's none of your business!"