Question: Continuing with project X from question 3 above; assume the following normal and crashing costs information as follows. Construct a working table which show the

 Continuing with project X from question 3 above; assume the following

Continuing with project X from question 3 above; assume the following normal and crashing costs information as follows. Construct a working table which show the activities you would crash and in which order. From this table, a) recommend the activities you would crash and for how many days you would shorten for each of these tasks, b) calculate the overall costs to achieve this, and c) determine what is the project duration after crashing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!