Question: Continuing with the construction project scenario from the previous question, the project team completes the desiogns (Task A0 and then begins construction (TaskB). What type
Continuing with the construction project scenario from the previous question, the project team completes the desiogns (Task A0 and then begins construction (TaskB). What type of dependancy describes the erelationship between Tasks A and B