Question: Continuous stop watch time study figures for a job are given below. Calculate the standard time for the job assuming total allowances are 15%.

Continuous stop watch time study figures for a job are given below.

Continuous stop watch time study figures for a job are given below. Calculate the standard time for the job assuming total allowances are 15%. Perfor Ele- Cycle Cycle Time minute ment 1 2 3 4 5 6 7 8 9 10 mance No. rating 1234 0.09 0.49 0.89 1.31 1.70 2.09 2.50 2.88 3.29 3.71 90 0.16 0.56 0.95 1.38 1.76 2.16 2.57 2.95 3.36 3.78 110 3 0.28 0.67 1.07 1.49 1.88 2.28 2.68 3.07 3.40 3.90 120 4 0.41 0.80 1.21 1.61 2.00 2.41 2.80 3.20 3.62 9.03 100