Question: Contract requirements state that a project must be completed within 1 8 0 working days, or it will incur penalties for late completion. Analysis of

Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an expected project completion time of 145 days with a project standard deviation of 20 days. What is the probability that the project will be completed before the late-payment deadline?
Group of answer choices
0.0401
0.4599
0.8056
0.9599

Step by Step Solution