Question: Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 484. What is the probability that the project will be completed after 149 working days and before the late -payment deadline?..
0.29
near 1.0000 or almost certain
0.37
0.68
0.95
Step by Step Solution
There are 3 Steps involved in it