Contractor A submits a request for equitable adjustment in the amount of $250,000. The REA is signed by the CEO, not certified, and asks for a Contracting Officers Final Decision. The Contracting Officer and Contractor A negotiate the amount for 3 weeks before the Contracting Officer denies the REA. Does Contractor A have a Contracting Officers Final Decision from which they can appeal? Why or why not? What piece of information is missing from this REA that might assist the Courts in determining whether it is a claim?