Question: Contribution Margin ABC current project 's sales details are as follows: Project Sales Revenues Project Cost (% of (RM) sales revenues) D 2,450,000.00 58% E

Contribution Margin ABC current project 's sales details are as follows: Project Sales Revenues Project Cost (% of (RM) sales revenues) D 2,450,000.00 58% E 1,380,000.00 63% F 2,000,000.00 47% The company is planning to undertake Project H which costs RM2.3 million, and is expected to bring in sales revenues of RM3.6 million. Project H will affect sales revenues of the existing projects by average of 20% each. Determine the viability of the proposed project. 22 2 points Total project cost of the existing projects is RM Type your answer... 2 points Contribution margin of Project E & F is RM_ Type your answer... 23 --00 --DO