Question: control. The contractors plan to procure the required soil from two different sites, as quoted below. Calculate the total cost ( haulage and placement )

control. The contractors plan to procure the required soil from two different sites, as quoted below. Calculate the total cost (haulage and placement) of the bids to verify the contractors' calculations. control. The contractors plan to procure the required soil from two different sites, as quoted below. Calculate the total cost (haulage and placement) of the bids to verify the contractors' calculations.
Company A
Distance from borrow pit to embankment: 28 miles
Cost of haul ($yd3-mile
Cost of fill material ($yd3):2.00
Borrow soil moisture content: 13%
Specific gravity of solids: 2.70
Degree of saturation: 70%
Company B
Distance from borrow pit to embankment: 35 miles
Cost of haul ($yd3-mile
Cost of fill material ($yd3): 2.40
Borrow soil moisture content: 12%
Specific gravity of solids: 2.71
Degree of saturation: 60%
The total cost (haulage and placement) for company A (million $)
The total cost (haulage and placement) for company B (million $)
Company A
Distance from borrow pit to embankment: 28 miles
Cost of haul ($yd3-mile
Cost of fill material ($yd3):2.00
Borrow soil moisture content: 13%
Specific gravity of solids: 2.70
Degree of saturation: 70%
Company B
Distance from borrow pit to embankment: 35 miles
Cost of haul ($yd3-mile
Cost of fill material ($yd3): 2.40
Borrow soil moisture content: 12%
Specific gravity of solids: 2.71
Degree of saturation: 60%
The total cost (haulage and placement) for company A (million $)
The total cost (haulage and placement) for company B (million $)
control. The contractors plan to procure the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!