Question: ControlQuestion content area Part 1 Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the plane took 1 8 0 0 0 hours
ControlQuestion content area
Part
Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the plane took hours to produce. Using an learning curve and a $perhour labor charge, he wants to determine the cost of the four additional planes.
Part
Time required for the fourth unit
enter your response here hoursround your response to the nearest whole number