Question: Coopers Copy Shop is considering a process for completing copying jobs brought in by customers. After some practice, the process can be completed with a

Coopers Copy Shop is considering a process for completing copying jobs brought in by customers. After some practice, the process can be completed with a standard time of 10 minutes for setup and 15 minutes for actual copying. Assume an 8 hours of working per day, what is the daily capacity assuming numerous repeated operations after an initial operation?

Group of answer choices

15

40

60

80

None of the above is an answer