Question: Cornerstone Exercise 12.1 (Algorithmic) Value- and Non-Value-Added Cost Reporting Cicleta Manufacturing has four activities: receiving materials, assembly, expediting products, and storing goods. Receiving and assembly

Cornerstone Exercise 12.1 (Algorithmic) Value- and Non-Value-Added Cost Reporting

Cicleta Manufacturing has four activities: receiving materials, assembly, expediting products, and storing goods. Receiving and assembly are necessary activities; expediting and storing goods are unnecessary. The following data pertain to the four activities for the year ending 2014 (actual price per unit of the activity driver is assumed to be equal to the standard price):

Activity

Activity Driver

SQ

AQ

SP

Receiving

Receiving orders

12,000

30,000

$21

Assembly

Labor hours

123,000

150,000

15

Expediting

Orders expedited

0

10,000

50

Storing

Number of units

0

20,000

7

Required:

Hide

1. Prepare a cost report for the year ending 2014 that shows value-added costs, non-value-added costs, and total costs for each activity. If an amount is zero, enter "0".

Cicleta Manufacturing

Value and Non-Value-Added Cost Report

For the Year Ended 2014

Activity

Value-Added Costs

Non-Value-Added Costs

Total Costs

Receiving

$

Correct 9 of Item 1

$

Correct 10 of Item 1

$

Correct 11 of Item 1

Assembly

Correct 13 of Item 1

Correct 14 of Item 1

Correct 15 of Item 1

Expediting

Correct 17 of Item 1

Correct 18 of Item 1

Correct 19 of Item 1

Storing

Correct 21 of Item 1

Correct 22 of Item 1

Correct 23 of Item 1

Total

$

Correct 25 of Item 1

$

Correct 26 of Item 1

$

Correct 27 of Item 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!