Question: Cornerstone Exercise 13.2 (Algorithmic) MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100
Cornerstone Exercise 13.2 (Algorithmic) MCE
Craig, Inc., has provided the following information for one of its products for each hour of production:
| Actual velocity: 100 units (per hour) |
| Move time: 11 minutes |
| Inspection time: 15 minutes |
| Rework time: 11 minutes |
Required:
1. Calculate MCE. If required, round your answer to two decimal places.
2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places.
| Theoretical cycle time | minutes | |
| Actual cycle time | minutes | |
| MCE |
3. What if waste is reduced by 30 percent? New waste = ? minutes
What is the new MCE? If required, round your answer to two decimal places. ?
What is the new cycle time? ? minutes

Cornerstone Exercise 13.2 (Algorithmic) MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 11 minutes Inspection time: 15 minutes Rework time: 11 minutes Required 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time Actual cycle time MCE 3. What if waste is reduced by 30 percent? New wasteminutes What is the new MCE? If required, round your answer to two decimal places. minutes minutes What is the new cycle time
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts