Question: CORRECT: (a) and (d) The critical path(s) is/ are the longest path(s) of a project and hence the length of the critical path(s) is the
CORRECT: (a) and (d)
The critical path(s) is/ are the longest path(s) of a project and hence the length of the critical path(s) is the minimum duration (shortest time) the project can be completed. By 'shortest' we mean that the project's duration cannot be reduced any further. Each activity of the critical path(s) has zero slack associated with them meaning any delay in these activities will lead to an equal amount of delay for the entire project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
