Question: CORRECT: (a) and (d) The critical path(s) is/ are the longest path(s) of a project and hence the length of the critical path(s) is the

CORRECT: (a) and (d)

The critical path(s) is/ are the longest path(s) of a project and hence the length of the critical path(s) is the minimum duration (shortest time) the project can be completed. By 'shortest' we mean that the project's duration cannot be reduced any further. Each activity of the critical path(s) has zero slack associated with them meaning any delay in these activities will lead to an equal amount of delay for the entire project.