Question: Correct Answer: It is under the planned cost. Why: The forecast at completion (EAC = $525,000) is less than the original budget at completion (BAC

Correct Answer: It is under the planned cost. Why: The forecast at completion (EAC = $525,000) is less than the original budget at completion (BAC = $550,000), indicating an expected underrun