Question: correct Question 3 Activity A E A project of seven activities is defined as follows: Immediate Predecessors Time (in wk) 4 9 F E 5
correct Question 3 Activity A E A project of seven activities is defined as follows: Immediate Predecessors Time (in wk) 4 9 F E 5 D A 2 C A 6 G F, D 3 K C, G 0 Which of the following statements is correct for Activity G's schedule? The earliest starting time is on the 6th day. The earliest finishing time is earlier than the latest starting time. The latest starting time is on the 14th day. Activity G has a slack time of eight days. 0/10 pts