Question: Cost and Estimation Budgeting, Project management Problems 323 8.19 Using the following information about work package bud- gets, complete the overall time-phased budget for your

Cost and Estimation Budgeting, Project management

Cost and Estimation Budgeting, Project management

Problems 323 8.19 Using the following information about work package bud- gets, complete the overall time-phased budget for your project. (All cost figures are in $000s). Which are the weeks with the greatest budget expense? Table for Problem 8.19 Task Budget Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 5 3 2 B 8 1 4 3 1 C 12 2 7 3 D 7 3 3 1 E 14 5 5 2 2 F 6 1 2 3 Plan 52 4 8 Cumulative 4 12