Question: Cost and schedule data for a small project are given below. Assume an indirect cost of SR 300/day. Activity Depends on Cost (SR) Time

Cost and schedule data for a small project are given below. Assume an indirect cost of SR 300/day. Activity Depends on Cost (SR) Time (days) A B C D E - A A A B, C & D Crash 4000 2000 1800 2000 1600 Normal 3000 1200 1000 1200 1600 Crash 4 2 3 3 3 Normal 5 6 4 5 3 1) Draw the project network and identify the critical path. 2) Crash the network fully to find out the minimum project duration. 3) Draw the contract total cost/time curve and determine the optimum duration of the contract.