Question: Cost ( budget ) risks include those issues, events, and conditions that may affect a project s having sufficient funds on a timely basis. Of

Cost (budget) risks include those issues, events, and conditions that may affect a projects having sufficient funds on a timely basis. Of the following, which is NOT a common type of cost (budget) risk?
A. defunding
B. cost estimation errors
C. incorrect task precedence relationships
D. cash availability