Question: Cost ( budget ) risks include those issues, events, and conditions that may affect a project s having sufficient funds on a timely basis. Of
Cost budget risks include those issues, events, and conditions that may affect a projects having sufficient funds on a timely basis. Of the following, which is NOT a common type of cost budget risk?
A defunding
B cost estimation errors
C incorrect task precedence relationships
D cash availability