Question: Cost control does not need to involve construction expertise from accounting staff True False QUESTION 36 An activity duration ruing construction should be no less
Cost control does not need to involve construction expertise from accounting staff True False QUESTION 36 An activity duration ruing construction should be no less than a. one hour b. one day c. three hours d. three days QUESTION 37 What type of sequencing relationship is used when the second activity does not start until the first one is completed? a. Start to Finish b. Finish to Finish c. Start to Start d. Finish to Start QUESTION 38 What type of sequencing relationship is used when two activities should be completed at the same time despite the fact that they might have different durations
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
