Question: Cost information from previous question: Fixed Cost Variable Cost per Unit Supplier A $ 0 $ 2 0 per unit Process B $ 8 0

Cost information from previous question:
Fixed Cost Variable Cost per Unit
Supplier A $0 $20 per unit
Process B $800 $10 per unit
Process C $2000 $4 per unit
At what point (P2) are you indifferent between Supplier A and Process C?
Group of answer choices
200 units
80 units
an infinite number of units
125 units