Question: Cost variance is computed by Select one: A. Subtracting BAC from ETC B. Subtracting actual cost from earned value C. Subtracting budget at completion from

Cost variance is computed by Select one: A. Subtracting BAC from ETC B. Subtracting actual cost from earned value C. Subtracting budget at completion from earned value D. Subtracting planned value fro