Question: could someone just show me how to get this answer A mortgage service office has the following four activities involved in approving a loan application.

A mortgage service office has the following four activities involved in approving a loan application. Note that a working day is 8 hours and there are 60 minutes in one hour. The office has three employees, activities A, B and C are combined together and assigned to two employees, while the other employee is responsible for the last activity D. What is the mortgage office's direct labor utilization (DLU) under this setting? Numbers only (e.g., 0.445 Is acceptable, but NOT 44.5\%), keep three decimals if not exact, either round up or down is ok 0.973 margin of error +/0.001 A mortgage service office has the following four activities involved in approving a loan application. Note that a working day is 8 hours and there are 60 minutes in one hour. The office has three employees, activities A, B and C are combined together and assigned to two employees, while the other employee is responsible for the last activity D. What is the mortgage office's direct labor utilization (DLU) under this setting? Numbers only (e.g., 0.445 Is acceptable, but NOT 44.5\%), keep three decimals if not exact, either round up or down is ok 0.973 margin of error +/0.001
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts