Question: Could you explain me how to obtain the probability, please? The critical path is A-C-F-H and the project completion time is 16.330 days . Problem

Could you explain me how to obtain the probability, please? The critical path is A-C-F-H and the project completion time is 16.330 days.

Could you explain me how to obtain theCould you explain me how to obtain the

Problem 5-10 (Algo) The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B C A D A E B F C D G DE H F,G TIMES (DAYS) b 1 2 3 1 4 7 2 11 1 5 9 1 2 3 1 4 7 1 2 3 2 3 3 0 Nm UI d. What is the probability of completing this project within 20 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round Intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.) Answer is complete but not entirely correct. Probability 0.9681

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!