Question: Could you help me with the following EANB problem? Question There are two projects under consideration: Project A has an NPV of $20m and will

Could you help me with the following EANB problem?

Question

There are two projects under consideration:

Project A has an NPV of $20m and will last three years.

Project B has an NPV of $60m and will last nine years.

It is anticipated that if either project is chosen it will be possible to repeat it for the foreseeable future. The interest rate is 1% per year. Which project will have a higher EANB and why?